Posts Tagged ‘Emergency’

KARE 11 Electrical Fire Prompts Emergency Response and Upgrades

Wednesday, August 13th, 2025

In the world of live television, there’s no pause button. A significant transformer fire at KARE 11’s Golden Valley, Minn. facility forced a full evacuation of the building. While there were no injuries, employees remained unable to access the facility, and the extent of damage to critical broadcast systems was initially unclear. Egan Company responded swiftly with a complete electrical infrastructure replacement to restore reliable operations and help KARE 11 return to normal broadcasting as quickly as possible.

The original electrical system installed in the 1970s by a contractor not affiliated with Egan Company — featured an outdoor, weatherproof-rated bus duct running above ground into the indoor utility room. Building engineers, facilities managers, and Egan experts believe that prolonged exposure to Minnesota’s severe weather over the past five decades contributed to the system’s failure. 

Jesse Gesme, Electrical Special Projects Project Manager, said, “It was great to see everyone come together with all hands on deck, multiple project managers, estimators, and outside vendors, working with urgency to restore operations. The teamwork and quick coordination with the KARE 11 team made a big difference in getting the job done.”

Egan crews mobilized immediately when they got the call to restore power and begin installing new electrical systems to meet modern codes and standards. By noon the following day, the temporary outdoor generator’s final  connections were made to  re-energize the station  and work began on the installation of new electrical services and infrastructure both inside and outside the building. The final switchover from generator power to the upgraded permanent system took place nine days after the fire.

“We rely on Egan’s expertise and the quality of their work — both of which have met or exceeded our expectations,” said Marty McAlpine, KARE 11 Broadcast Engineer. “We valued their collaboration, approachability, and continual communication as the project progressed. The crew was with us every step of the way. It was clear they had our best interests front and center. Every day, multiple times throughout the day, they kept us in the loop and synced up at every stage of the project. They listened and understood our business needs and operations and answered every question we had. There were no shortcuts or loose ends. They were always on time, worked as long as it took, and ultimately completed the work on schedule.”

Safety remained the top priority throughout the process, consistent with Egan’s “Stay Safe” core value. Crews worked closely with KARE 11 staff to ensure operations continued without risk to employees or visitors. Station leadership has expressed confidence in Egan’s handling of the emergency and its commitment to quickly restoring reliable electrical service.

Calling on Trusted Relationship Amid Sudden Loss of Power

Monday, November 14th, 2022

At 5 a.m. on a Monday, an office tower in Brooklyn Park, Minn. experienced a complete loss of power. The culprit? Exterior bus duct corroding over time later leading to an explosion at the site, cutting all power to the building. With various tenants soon to be occupying the building that day, the property manager, MetroPlains Management, made quick decisions when it came to a reliable solution to the problem. 

Enter: Egan Company.

As a long-time customer, MetroPlains properties across the Twin Cities have been cared for by Egan employees for years. MetroPlains Management Property Manager, Jason Sklar shared, “Egan has been our primary partner for years for routine day-to-day work and significant tenant build outs in office buildings.” Having this established relationship to rely on made decision-making easy when facing this complex issue.

“Late this summer, one of our office buildings had a major power outage that damaged main feeder lines as well as the primary transformer, disrupting power to the entire building. Egan Company, with Project Manager Brent Fritz and a highly skilled trades team, came to the rescue. They had a crew on site immediately and worked with Xcel Energy to plan a temporary fix and install new transformers and temporary feeder lines. Fritz was onsite managing the crisis to ensure we had the best crew working on the problem. Working hand-in-hand with Xcel Energy, our building was back up and running the same day, much to our tenants delight,” explains Sklar.

Owning the Challenge

While the temporary solution was able to tide the building over, the team quickly worked to create a long-term solution with property safety in mind. Once the plan was in place, the work was executed swiftly by Egan electricians. The facility was switched from temporary generators to the permanent system before tenants returned the next day.

“Now our office building is better than ever with updated electrical systems. Egan has ‘owned the challenge’ of taking care of their customers when they need it the most. Thanks to this highly skilled team!” said Sklar.

At Egan, it’s our goal to not only aid in large scale, planned needs and updates, but also to have our customers’ backs in emergency situations. “Owning the challenge” means ensuring that the job is done right, and done safely – every time. According to Sklar, “Fritz continued to work with our property management team throughout to aid in the process of insurance claims adjusters in order to effectively restore our lost infrastructure.” Our response means seeing the project through, from start to finish.

“When it comes to field leaders like Deland Croze, I have the utmost confidence in their ability to make and carry out the best plan of attack.” Brent Fritz, Egan Company Project Manager, reflects. “With the outcome of the project in hands as capable and experienced as Croze’s, this project was sure to be completed accurately and on-time.” 

What could have resulted in a costly, extended process was streamlined by one simple rule: a strong partnership.

(The Egan team on the project included: Brent Fritz, Deland Croze, Valdemar Scherer, Chad Hughes, and John Tupy).